Work and Labour — Wages Protection and Contractors' Liens Act — Time for claim and date of completion — Uncompleted work taken out of contract to be completed in a new contract — Completion certificate for completed work under original contract not binding on subcontractor — Wages Protection and Contractors' Liens Act 1939, ss 20(2), 34(4), (6).