High Court Wellington
1 March; 2 March 1954
Gresson J
1 March; 2 March 1954
Gresson J
Wages Protection and Contractors' Liens — Contract to supply All Joinery required for Erection of Building — Separate Ledger Account for Same — Sufficiently Precise Contract to support Charge of Lien — Contract Completed when Last Article of Joinery delivered — Timber and Hardware supplied under Separate Orders under Agreement to furnish Such Timber and Hardware as might be required — Contract of General Character so that Each Order a Separate Contract — Valid Lien in Respect of Items supplied within Thirty Days of giving Notice — Wages Protection and Contractors' Liens Act, 1939, ss 21, 26 (2).