High Court Wellington
28 July; 25 August 1972
Mahon J
28 July; 25 August 1972
Mahon J
Building contracts, engineers and architects — The contract — Implied terms — No implied negative term that owner would not revoke builder's licence to go on the site — Forfeiture — Exercise of right to forfeit — Builder not entitled to injunction preventing owner completing works.