Site Information

 Loading... Please wait...

Moyes & Groves Ltd v Radiation New Zealand Ltd - [1982] 1 NZLR 368

$30.00

Court of Appeal Wellington
6 August; 10 September 1982
Cooke, Somers and Ongley JJ
Contract — Consideration — Effect of delay on original contract — Goods, manufactured overseas specifically for buyer, arrived two years late — By the time goods arrived, seller and buyer had forgotten about contract — Seller willing to supply goods at cost but cost had increased from $400 to $2737 - Buyer accepted seller's price "under protest" but after delivery paid only $400 - Seller sued for balance — Whether compromise constituted good consideration — Whether economic duress was a ground for avoiding liability under a contract.