High Court Wellington
13, 14, 15, 16, 20, 21, 22, 23 February; 1, 2 March; 21 July 1978
Casey J
13, 14, 15, 16, 20, 21, 22, 23 February; 1, 2 March; 21 July 1978
Casey J
Building contracts, engineers and architects — Authority of Engineer — Variations — Extension of time — Fixed price agreement signed on NZSS form 623 — Owner's Engineer and Engineer's Representative authorised extras increasing cost — Whether delegation to Representative valid — Whether extras validly authorised — Whether Engineer can grant extension of time after completion date — Whether completion certificate once issued can be withdrawn — Whether certificate final.