High Court Wellington
1 August; 28 November 1974
MacArthur J
1 August; 28 November 1974
MacArthur J
Building contracts, engineers and architects — Damages — Breach of contract by contractor — Employer subsequently selling building without any loss by reason of default.
Damages — Measure of damages in contract — Breach of building contract by builder — Employer selling building subsequently without loss of price in respect of breach — Employer entitled to damages being the difference between the actual cost to builder and the amount it would have cost him had the contract been properly performed.